Saturday, February 18, 2017

NTDC asked to change power transmission line route

AJK-EPA says that the hydropower project’s line route would impact the environment

The Azad Jammu and Kashmir Environment Protection Agency (AJK-EPA) has taken strong exception to the impending loss of vegetative cover along the proposed route of transmission line of a hydropower project in view of its environmental impact on the city of Muzaffarabad. 
The agency has asked the National Transmission and Despatch Company (NTDC) to halt the process at the earliest and find some alternative route to avoid environmental degradation in the area.
The 147-megawatt Patrind hydropower project has been built by a Korean company – Star Hydropower - on build-operate-own-transfer (BOOT) basis and likely to be commissioned sometime next month.
The powerhouse is located along the right bank of River Jhelum across the Lower Chattar neighbourhood of Muzaffarabad.
On Feb 7, the EPA director general, Chief Conservator of Forests and a technical team from the NTDC had visited the project site and after detailed deliberations with experts, the EPA had informed all stakeholders in unequivocal terms that the current route proposed for power transmission was not viable in terms of environmental approach. 
According to an EPA document, addressed to NTDC and copied to top AJK government functionaries, the patch of the forest, proposed to be hacked, was in the immediate vicinity of Muzaffarabad city and contributed to its beauty, visual amenity and biodiversity (ecological) services for human beings. 
Additionally, cutting of Chir Pines in such a big number with such age and height was also bound to cause biomass loss amounting in thousands of tons, which could not be compensated in centuries, let alone years, added the document.  
View of the mountain before construction of project
view of the mountain after construction of project 
The EPA document said that the project had already caused significant erosion of green vegetation comprising large size Chir pine trees, shrubs and a miscellany of floral species. 
The magnitude of irreversible changes that the project had already made to the vegetative cover at the powerhouse site could be assessed from Google imagery, before and after its execution, it added. 
“In case the NTDC finds itself with no other option for power evacuation except hacking dense forests for the purpose, it will contribute to an irreparable environmental loss, in sheer disregard to the very concept of ‘sustainable development’ and thus impermissible by law,” the EPA document read. 
The EPA warned that in case the dense canopies of exiting fully-grown Pine trees were chopped down, landslide would occur and eventually aggravated by huge top load (spoil) and sharp gradient of the area, thus putting the sustainability and viability of the project, particularly the powerhouse, at stake. 
The EPA regretted that Star Hydropower had “unilaterally” changed the design of the project by shifting switchyard from a designated and approved site on the left bank of river to the right bank without prior intimation and approval of the agency.
The AJK Environmental Protection Act of 2000 explicitly stipulates that “no proponent of a project shall commence construction or operation unless he has filed with EPA an Initial Environmental Examination or where the project is likely to cause an adverse environmental effect, an Environmental Impact Assessment, and has obtained from the EPA approval in respect thereof.” 
Even the NTDC had neither formally informed nor applied for environmental NOC under law, or else this situation could have been averted, the EPA said. 
The EPA has maintained that the present critical state of affairs with reference to environmental adverse impacts was, ostensibly, developed as a result of ignorance of both the Star Hydropower and the NTDC, for they had not followed AJK’s environmental law in letter and in spirit.
“In order to propose a viable way forward, a committee comprising the technical experts of NTDC, Star Hydropower and AJK Forests Department should be constituted to look for the alternatives aimed at securing the natural resources in compliance of the objectives of sustainable development,” suggested the agency. 
Earlier, in response to the EPA’s concerns about the felling of Pine trees for the transmission line, the NTDC had maintained that if the latter failed to install HT line for evacuation of power by interconnecting with local grid station Muzaffarabad-II (Rampura), the Central Power Purchasing Agency (CPPA) will have to pay penalties (to the Korean company). 
When this scribe contacted EPA Director General Raja Mohammad Razzaque, he confirmed that his office had conveyed concerns to all relevant persons in the interest of environment of the area. 
Tariq Naqash 

No comments:

Post a Comment